Current and upcoming construction projects are listed in order of Begin Construction Date.
Review contractors, architects, RFP, RFQ, status of projects.
CORA Requests (Colorado Open Records Act) |
||
All public record requests must be sent to: (preferably in writing rather than email) |
State of Colorado State Buildings Program Documents and Forms
Replace University Hall RTU's at the UCCS Campus
|
|||||||||
Heller Properties Rehabilitation
|
|||||||||
Science Engineering Construction - begun August 2006
| Project will create a science and engineering complex, adjacent and connected to the existing engineering building. Significantly expanding the science and engineering capabilities of the campus. | |
Project Manager Project Architect Commissioning Services Provider |
![]() |
| Project Specs |
RFP-revised Commissioning Services (Cx) Addendum to RFP Commissioning Services Science/Engineering website-see for design floor plans, relocation information and additional project updates |
| Project Status | |
| Architect selected Gerald H. Phipps selected as CGMC Project registered to become LEED certified Leed consultant selected Commissioning Services Selected Groundbreaking held June 29, 2006, Site fencing July 2006 Design drawings are being completed-currently at Construction Bid Construction completion projected for late spring 2009 |
|
| The Events Center will consist of an addition to the existing University Center of approximately 27,000 gross square feet located adjacent to the existing gymnasium, with an upper level connection to Dwire Hall. The building will be faced with brick, and aluminum storefront and glass to be architecturally compatible with the existing buildings. The main interior space will be a single level multi-use space accommodating a gymnasium with collapsible bleachers to seat 1,400 spectators. Ancillary spaces will be accommodated on three levels next to the multi-use space. | |
Project Architect and LEED Consultant : |
![]() ![]() |
| Project Specs | Utilities Infrastructure UCCS Events Center Mandatory meeting sign in roster
|
| Project Status | |
Regents approved project at last meeting |
|
| Conduct an Historic Assessment of the Heller Property for development of a site master plan. | |
| Project Architect: Aller-Lingle |
![]() |
| Project Specs | Historic Assessment and Master Plan: Heller Property RFP SHF contact: Anne McCleave, 303-866-3536 anne.mccleave@chs.state.co.us |
| Project Status: FINAL HISTORICAL ASSESMENT FOR HELLER PROPERTY | |
Available in hard copy at commencement of the project: "Intensive Cultural Resources Survey: Cragmor Campus, University of Colorado at Colorado Springs, El Paso County, Colorado", by William R. Arbogast, Kim Carsell, Heather Gerhart, and Kim Kersey. Prepared for UCCS by William R. Arbogast, Principal Investigator, Colorado Permit 98-25, Colorado State Historical Fund Grant #98-02-026, March 25, 1999. |
|
Cancer Survivor's Park - begun Fall 2007
| Project will create a new recreation area along Austin Bluffs Parkway dedicated to survivors of Cancer. Donated in cooperation with the Bloch foundation |
|
Project Architect Construction Contractor |
![]() |
| Project Specs |
|
| Project Status | |
| Regents approved lease of 25 acres to Bloch Foundation Design pending approval from UCCS, DRB, and Bloch Foundation Construction scheduled to begin fall 2007 |
|
| Project is to create storm water drainage improvements for parking lot 9, re-milling for lots A and 9 | |
| Please note that the Bid Due date changed to May 28th at 2:00 pm | |
| Project Specs |
Sign-in roster from mandatory meeting Contractors agreement |
Questions: Please provide clarification of the items listed below:
Responses:
Cheryl Bean |
|
Cragmor Watermain Replacement Project
| Project is to replace watermain at Cragmor Hall | |
| Project Specs | Sign in roster from mandatory meeting Contractors Agreement MWBE UI |
| Company: | Bradley Excavating |
| Project is to renovate existing Science Building within exterior walls. Includes lab, classroom and office space. | |
Project Architect: Anderson Mason Dale Construction Contractor: |
|
| Project Specs |
A/E Request for Qualifications |
| Questions and Responses: | |
Q. A. |
|
| Project is to install LED signage on the exterior of University Hall to highlight Theatreworks and UCCS events to passing motorists. | |
| Project Specs | |
Questions: Theatreworks LED Sign Q&A |
|
Company: Sign Shop Illuminated |
|
Repair/Replace RTUs University Hall
| To replace 27 Roof Top Units at University Hall | |
| Project Specs | RTU RFQ - Revision 7/11/08 Sign in Roster for 01/26/09 Mandatory Meeting
|
| Questions: | None submitted |
| Architect/Engineer: | Schendt Engineering |
Summit Green Artificial Turf Project
| Project is to install Artificial Turf at the Summit Village | |
| Project Specs | Documented Quote Publication |
Questions: Summit Green Articial Turf Q&A |
|
| Project Company: | Performance Surfacing |
Solar Panels - Recreation Center
| Project is to provide a Design/Build of a solar thermal pool heating system for the Campus Recreation Center | |
| Project Specs | |
| Questions: | |
Noven Solar Incorp. |
|
| Project is to find a qualified firm to provide a Design/Build installation of a thin film photovoltaic system for the Science Engineering building. | |
| Project Specs | |
Questions: Questions and Answers
|
|
| Amendments: | Amendment #1 |
| Project Company: | Douglass Colony Group |
09/10 Standing Order Contract for Small Projects
Prequalifiy for Standing Order Contract list for UCCS small projects under $150,000.00 |
|
| Project Specs | |
Questions: |
|
| Amendments: | |
| Project Company: | |
09-051 Engineering Building Renovation Phase I
Project to partially renovate and upgrade the research and office wing (east wing) of the existing Engineering building. |
|
| Project Specs |
|
| Questions: | |
| Amendments: | |
| Project Company: | RMH GROUP Matrix |
This project is new construction on undeveloped property for an approximately 33,000 gsf classroom, office and health facility. It will be located on the UCCS campus in the area known as University Summit. The project will also include site analysis, site development and utility extensions to the site. A Program Plan is being developed but is not available at this time. However, it is anticipated that that the facility will house the UCCS Psychology department, UCCS Aging Center and potentially, in partnership, Peak Vista Community Health Center. |
|
| Project Specs |
|
| Questions and Answers For the Project South Hall – Phase 1 Question In regards to your program for the South Hall Phase I project, we are interested in achieving a better understanding of the breakdown of your space as it relates to the classroom/education portions and what appears to be more clinical areas focused on psychology, the Aging Center and your proposed Peak Vista Community Health Center. Answer Question Answer Question Answer Question Answer Question Answer Question Answer Question Answer Question: We have recently been alerted to a storm which may cause UCCS’ closure tomorrow. Answer:
|
|
| Amendments: | MANDATORY MEETING LOCATION FOR SOUTH HALL PHASE 1, FRIDAY, APRIL 10 AT 2:00 HAS CHANGE TO: UNIVERSITY CENTER 116 |
| Project Company: | FINAL Matrix for Architect Selection |
09-063 West Lawn Grading and Flatwork
Project includes demolition of existing parking lot area of approx. .07 acres followed by over lot grading; minor storm sewer improvements; demolition and rebuilding 175 lineal feet of road including curb and gutter with asphalt; installation of approx. 500 lineal feet of concrete fire lane and "signature" pedestrian spine. |
|
| Project Specs |
|
Questions: 1. Do you have any landscape or irrigation drawings that you can provide for reference. A: NO 2. Can you provide numbered address for Eagle Rock storage area. A: Behind the Eagle Rock Modular buildings which are referred to as buildings 201 to 204 on the UCCS Campus Map. 3. Can you provide numbered address for Nevada storage area. A: The area is located north of the drainage way which is north of the Four Diamonds Sports Complex at 5025 N. Nevada Avenue. 4. The re-grading south of the pedestrian spine will be regarded, what will the finished product be for landscaping? Will this area be irrigated if sod or seeded? A: Sod with irrigation
6. Can we use a temporary metal concrete wash out in lieu of a permanent dug in type? A: Temporary wash out is acceptable but must be in sufficient quantity and size to contain all liquid and concrete waste generated by washout operations. 7. Bid Form, item 8, please clarify what is required with regard to the reference to submit wage rates for the prime and subcontractors. A: The construction documents do not contain a specific request for wage rates - therefore these are not required. 8. General Conditions, page 8, article 9, B, states that the contractor shall secure and pay for all permits required to complete the work. In addition to the erosion control permit, please specify those that are required. A: No other permits are required beyond the CDPHE Stormwater Construction Permit. 9. General Conditions, page 20, article 25, Insurance, C, Builders Risk Insurance, if it is desired that the general contractor include in their bid a builders risk policy, please state the amount of coverage the policy should be based on, otherwise, confirm none is required. A: Builders Risk Insurance is not required for projects under $1,000,000. 10. Section 01 50 00 Temporary Facilities & Controls, 3.02, C, please specify the reference to “trucked in electrical service”. Is this a requirement of this project or left over from another? For no more electricity than we will need during construction, couldn’t we just use the existing facilities? Similar question with regard to water. A: The Owner does not provide utility services for use by the Contractor. The Contractor shall provide a power source as needed, and either truck in water or secure a Temporary Water Service Permit (Fire Hydrant Use) from Colorado Springs Utilities. 11. Section 01 51 00, is it required that the construction staking be completed by a licensed surveyor? Please clarify exactly what the owner will provide, with regard to a project benchmark and electronic grading information. A: Yes - construction staking must be performed by a licensed surveyor. Owner will provide temporary site benchmark locations (which are tied to the Colorado Springs Utilities FIMS control), and a CAD file with contours, spot elevation, and improvement locations which shall be used in conjunction with the plan and profiles. 12. Section 31 20 00, is there a soils report available for the existing on site soils expected to be encountered in the over excavated area below the existing pavement, as discussed during the pre-bid meeting? A:Soil information will be posted on the West Lawn project listing under the UCCS Facilities Service Department. 13. Section 32 12 16, 2, B, 2, states that soft spots encountered during the proof rolling operation shall be repaired at the contractor’s expense? Please specify the quantity and exact size of the referenced soft spots so that we can include them in our bid, otherwise, state that the repair of the soft spots will be accomplished through a change order or unit price proposal. A: If soft spots are highlighted during proof rolling - any additional direction to the Contractor will be provided in a change order. 14. Section 32 13 13.3, 3.16, D, please clarify that in addition to applying curing compound to all new horizontal concrete surfaces, it is also required to cover the referenced surfaces for 7 days with 6 mil plastic? A: All portions of concrete spine (regular and colored concrete) shall be cured with liquid membrane forming curing compound and shall not be covered with plastic sheeting. 15. Sheet CO.O, Coordination Requirements, note 3, can the pedestrian spine mock up be a part of the permanent work? A: Yes if the entire mock up is acceptable to Owner. 16. Sheet C2.0, what is minimum thickness of the import top soil? A: 10 inches. 17. Sheet C2.0, note 16, is it desired to remove the existing rectangular storm inlet and grated cover and replace with a 4’ diameter concrete manhole with solid cover? A: Yes. 18. Is caulking of the joints at the location of dissimilar concrete colors required? A: the plans do not include this. 19. Please clarify the colored concrete requirements in terms of pounds of color per sack of cement. Is the specified 4% Chromix 1589 Durango Brown equal to a 4 lbs./cy color mix? (Manufacturers have different names for their available colors and most manufacturers indicate the amount of color in terms of pounds of color per 94 lb. sack of cement.) A: do what the color card you took the color from indicated. 20. How long are the “ #4 tie bars ”. Are they simply rebar dowels? Is it intended that they be located on each side of both the longitudinal and transverse 24” wide colored strips, extending in to all sides of the grey infill’s/strips? (or just the outside of the longitudinal strip as indicated on the addendum drawing?) A: See addendum #2. 21. Is caulking of the joints at the location of dissimilar concrete colors required? A: No. 22. Please clarify the colored concrete requirements in terms of pounds of color per sack of cement. Is the specified 4% Chromix 1589 Durango Brown equal to a 4 lbs./cy color mix? (Manufacturers have different names for their available colors and most manufacturers indicate the amount of color in terms of pounds of color per 94 lb. sack of cement.) A: The Chromix colors work as an additive that is premeasured and added per cubic yard of concrete. 23. How long are the “ #4 tie bars ”. Are they simply rebar dowels? Is it intended that they be located on each side of both the longitudinal and transverse 24” wide colored strips, extending in to all sides of the grey infill’s/strips? (or just the outside of the longitudinal strip as indicated on the addendum drawing?) A: See addendum #2. |
|
| Amendments: | |
| Project Company: | Pioneer Sand Company |
09-064 Science Bldg. Hazardous Materials Removal
|
||||||||
10-018 Alpine Village Landscaping
|
||||||||
Page content created by Facilities Services Department
Last updated Wednesday, November 18, 2009