Schedule for Construction

Completion of construction of Science Engineering Buildings -Phase 1: Late Spring 2009
Timeline
Construction
Ground Breaking July 2006
Set up construction Site June-August 2006
Construction Phase August 2006 - January 2009
Bid opening August 7, 2007
Add Alternates decided week of August 20, 2007
Relocation plans completed September 2008
Furniture orders completed January 2009
Beneficial Occupancy-depending on which alternates picked up Late Spring 2009
Relocation
Moves into the new building will begin after Beneficial occupancy is obtained, before classes begin Fall 2009 Summer 2009
Move and furniture coordinators selected March/April 2008
Faculty/Staff room assignments in SciEng determined April 14, 2008
Furniture hierarchies selected May 2008
Room layouts-offices, public space, conference rooms September 2008
Furniture/equipment selected/designated for purchase or move September 2008
Orders for furniture assembled/placed December 2008
Move plans finalized, movers hired Spring 2009
Pre move process-clean out, streamline, labeling, preliminary packing Early summer 2009
Moves into completed building Summer 2009
Open for classes Fall 2009

Please see Updates page for continuing Field Reports on the progress of Science Engineering Complex

Page content created by Facilities Services Department