Science & Engineering Buildings
|
Schedule for Construction
Completion of construction of Science Engineering Buildings -Phase 1: Late Spring 2009
| Timeline |
| Construction |
| Ground Breaking |
July 2006 |
| Set up construction Site |
June-August 2006 |
| Construction Phase |
August 2006 - January 2009 |
| Bid opening |
August 7, 2007 |
| Add Alternates decided |
week of August 20, 2007 |
| Relocation plans completed |
September 2008 |
| Furniture orders completed |
January 2009 |
| Beneficial Occupancy-depending on which alternates picked up |
Late Spring 2009 |
| Relocation |
| Moves into the new building will begin after Beneficial occupancy is obtained, before classes begin Fall 2009 |
Summer 2009 |
| Move and furniture coordinators selected |
March/April 2008 |
| Faculty/Staff room assignments in SciEng determined |
April 14, 2008 |
| Furniture hierarchies selected |
May 2008 |
| Room layouts-offices, public space, conference rooms |
September 2008 |
| Furniture/equipment selected/designated for purchase or move |
September 2008 |
| Orders for furniture assembled/placed |
December 2008 |
| Move plans finalized, movers hired |
Spring 2009 |
| Pre move process-clean out, streamline, labeling, preliminary packing |
Early summer 2009 |
| Moves into completed building |
Summer 2009 |
| Open for classes |
Fall 2009 |
Please see Updates page for continuing Field Reports on the progress of Science Engineering Complex
Page content created by Facilities Services Department This page last updated on Monday, April 07, 2008
|